DISTRIBUTION LINES



Name of Project
POWER TRANSMISSION LINE INSTALLATION BANDIRMA TRANSFORMER SUBSTATION, AKCAPINAR 1
Place BALIKESIR
Employer TEDAS BALIKESIR POWER DISTRIBUTION ENTERPRICE
Contract Date 06.09.1991
Completion Date 30.11.1992
Amount of Project (USD) 855,000
Name of Project POWER TRANSMISSION LINE INSTALLATION FOR GERMIYAN TRANSFORMER SUBSTATION - ILDIR 2
Place IZMIR
Employer TEDAS IZMIR POWER DISTRIBUTION ENTERPRICE
Contract Date 20.09.1991
Completion Date 05.03.1992
Amount of Project (USD) 217,000
Name of Project POWER TRANSMISSION LINE INSTALLATION FOR IRRIGATION, MANISA KIRKAGAC-ALASEHIR 3
Place MANISA
Employer TEDAS MANISA POWER DISTRIBUTION ENTERPRICE
Contract Date 16.06.1992
Completion Date 10.11.1992
Amount of Project (USD) 518,000
Name of Project POWER TRANSMISSION LINE INSTALLATION FOR IRRIGATION, GONEN SARIKOY MARMARA-TOPAGAC 4
Place BALIKESIR
Employer TEDAS BALIKESIR POWER DISTRIBUTION ENTERPRICE
Contract Date 10.07.1992
Completion Date 28.01.1993
Amount of Project (USD) 281,000
Name of Project POWER TRANSMISSION LINE INSTALLATION, BEYLIKDUZU TRANSFORMER SUBSTATION, ISISO DISTRIBUTION SUBSTATION 34.5kV 2x(3x477MCM) 5
Place ISTANBUL
Employer BOGAZICI POWER DISTRIBUTION INC.
Contract Date 14.09.1992
Completion Date 12.07.1995
Amount of Project (USD) 1,290,000
Name of Project POWER TRANSMISSION LINE INSTALLATION MARMARA DISTRIBUTION SUBSTATION TO SARAYLAR PTL 6
Place BALIKESIR
Employer TEDAS BALIKESIR POWER DISTRIBUTION ENTERPRICE
Contract Date 09.01.1995
Completion Date 29.11.1995
Amount of Project (USD) 1,453,000
Name of Project POWER TRANSMISION LINE INSTALLATION ASLANLAR TRANSFORMER SUBSTATION - KUTLUTAS P.T.L. CONNNECTION POINT TAMSA P.T.L. 34,5 kV 3X3/0 AWG 4,408 km. 7
Place IZMIR
Employer TAMSA SERAMIK (TEDAS IZMIR)
Contract Date 16.02.1995
Completion Date 06.06.1995
Amount of Project (USD) 1,781,000
Name of Project POWER TRANSMISSION LINE INSTALLATION FOR SARUHANLI FIELD IRRIGATION 8
Place MANISA
Employer TEDAS MANISA POWER DISTRIBUTION ENTERPRICE
Contract Date 08.08.1995
Completion Date 22.04.1996
Amount of Project (USD) 480,000
Name of Project POWER TRANSMISSION LINE INSTALLATION FOR SAVASTEPE, KEPSUT, DURSUNBEY FIELD IRRIGATION 9
Place BALIKESIR
Employer TEDAS BALIKESIR POWER DISTRIBUTION ENTERPRICE
Contract Date 04.09.1995
Completion Date 23.09.1996
Amount of Project (USD) 548,000
Name of Project POWER TRANSMISSION LINE INSTALLATION FOR KEMALPASA - SIRALIKTEPE R/L STATION 10
Place IZMIR
Employer TURK TELEKOMUNIKASYON INC
Contract Date 08.07.1996
Completion Date 30.07.1997
Amount of Project (USD) 107,000
Name of Project POWER TRANSMISSION LINE INSTALLATION FOR TAHIIRINI, ERDEMLI-GULBAYIR, KAVAK-GULBAYIR, YESILHISAR-BASKOY GROUP NO: 96.38.05 11
Includes Place Completion Date
Tahirini Grubu ENH KAYSERI 28.11.1997
Erdemli-Gulbayir ENH KAYSERI 17.03.1997
Kavak-Gulbayir ENH KAYSERI 17.03.1997
Yesilhisar-Baskoy ENH KAYSERI 27.11.1997
Employer KAYSERI AND SUBURBS POWER DISTRIBUTION INC.
Contract Date 15.08.1996
Amount of Project (USD) 580,000
Name of Project INSTALLATION OF GALVANIZED IRON POLES FOR PINARCIK BAHCECIK DAM 12
Place KAYSERI
Employer KAYSERI AND SUBURBS POWER DISTRIBUTION INC.
Contract Date 04.10.1996
Completion Date 18.12.1996
Amount of Project (USD) 8,000
Name of Project CAYIRHAN POWER TRANSMISSION LINE 13
Place ANKARA
Employer PARK TEKNIK CO.
Contract Date 08.04.1997
Completion Date  
Amount of Project (USD) 234,000
Name of Project POWER TRANSMISSION LINE INSTALLATION FOR KARAKUYU-K.SEKISI, BAHCECIK POWER PLANT GROUP NO: 97.38.14 14
Includes Place Completion Date
Karakuyu-K.sekisi ENH KAYSERI 10.03.1998
Bahcecik Baraji ENH KAYSERI 05.04.1999
Employer KAYSERI AND SUBURBS POWER DISTRIBUTION INC.
Contract Date 06.06.1997
Amount of Project (USD) 736,000
Name of Project AKHISAR TM - AKHISAR OSB ENH INSTALLATION 2(3x477 MCM) 9.030 km 15
Place MANISA
Employer AKHISAR OSB BOARD OF DIRECTORS
Contract Date 19.06.2001
Completion Date 17.10.2001
Amount of Project (USD) 798,000
Name of Project SINOP TM SINOP OSB ENH INSTALLATION 2(3x3/0 AWG) 9.000 km 16
Place SINOP
Employer SINOP OSB ENTERPRISING ORGANIZATION
Contract Date 15.05.2001
Completion Date 01.02.2002
Amount of Project (USD) 971,000
Name of Project BAKU-TBILISI-CEYHAN CRUDE OIL PIPELINE
PT-2 ELECTRICAL DISTRIBUTION NETWORK
25 KM 1X3/0 AWG CONDUCTOR
17
Place ERZURUM
Employer BOTAŞ GEN. DIR. BAKU-TBILISI-CEYHAN CRUDE OIL
PIPELINE PROJECT DIR.
Contract Date 31.05.2004
Completion Date 01.10.2004
Amount of Project (USD) 943,000
TOTAL 11.800.000